Perth Grammar School Upgrade


Advanced Search

 
 

Perth Grammar School Upgrade

As part of an extensive upgrade programme for those Perth & Kinross secondary schools that are not part of the Investment In Learning (IIL) Programme, upgrade works at Perth Grammar School have commenced.

Phase One

This first phase of the work was completed in April 2010 and comprised:

  • the complete refurbishment of 4 Science laboratories, with new custom-designed and fitted laboratory furniture;
  • the creation of an additional science laboratory by converting and refurbishing existing accommodation;
  • the complete refurbishment of the physical education department, including upgrade to 6 pupil changing rooms and associated shower and toilet facilities, upgrade to staff changing and toilet facilities and the creation of a disabled toilet and changing facility for the department;
  • the complete refurbishment of a further 6 toilet blocks and the creation of a disabled toilet facility;
  • review and upgrading of heating and radiators;
  • review and upgrading of electrical and services infrastructure;
  • extensive works to ensure that the establishment is made accessible and compliant with the requirements of relevant Disability Discrimination legislation.

In particular, the works to improve accessibility involved:

  • the installation of a ramp;
  • review and upgrade of handrails in various areas;
  • the undertaking of a programme to review and replace doors in various areas.

Phase Two

Additional funding announced as part of the budget setting process for 2012/13 - 2016/17 allows Phase Two works to commence.  This work will comprise:

  • Major infrastructure improvement which is likely to include electrical and data rewiring and upgrade, alarm and emergency systems renewal, heating systems renewal, energy conservation and other infrastructure and system efficiency improvements;
  • Upgrade of 6 Craft, Design & Technology rooms;
  • Upgrade of 3 Science laboratories;
  • Upgrade of 2 Home Economics rooms.

Consultation

Extensive liaison will continue to take place between school Management and Projects Support Team representatives to ensure that the minimum of disruption is caused to learning and teaching at the school throughout the construction works.

Last updated | 13/04/2012

   