Investment in Learning - Key Milestones
Last updated | 12/12/2007
The key milestones for the development of the Investment in Learning Programme are shown in the table below:
| Key milestones | Timing |
| Appoint advisers |
April 2003 |
| Committee decision on revised scale of project |
13 Aug 2003 |
| Committee decision on rescoping |
13 Aug 2003 |
| Develop ITN |
Ongoing to Feb 2003 |
Submit revised OBC to Scottish Executive for approval |
30 Sep 2003 |
| OJEU notice |
End Dec 2003 |
| Bidders conference |
27 Jan 2004 |
| Pre ITN key stage review |
mid Jan 2004 |
| Issue ITN |
10 Sep 2004 |
| Receive bids |
14 Jan 2005 |
| Bid assessment and negotiation commences |
17 Jan 2005 |
| Announcement of preferred bidder |
24 April 2006 |
| Commercial Close |
Autumn 2007 |
| Financial Close |
4 October 2007 |
| Construction phase commences |
Autumn 2007 |
| Construction ends with commissioning |
2009-2011 |
| Schools open |
2009- 2011 |
Key: OBC = outline business case, ITN = invitation to negotiate, OJEU = Official Journal of European Union |
|