Key milestonesTiming
Appoint advisers April 2003
Committee decision on revised scale of project 13 Aug 2003
Committee decision on rescoping 13 Aug 2003
Develop ITN Ongoing to Feb 2003

Submit revised OBC to Scottish Executive for approval 

30 Sep 2003
OJEU notice End Dec 2003
Bidders conference 27 Jan 2004
Pre ITN key stage review mid Jan 2004
Issue ITN 10 Sep 2004
Receive bids 14 Jan 2005
Bid assessment and negotiation commences 17 Jan 2005
Announcement of preferred bidder                24 April 2006
Commercial Close Autumn 2007
Financial Close 4 October 2007
Construction phase commences Autumn 2007
Construction ends with commissioning 2009-2011
Schools open 2009- 2011

Key: OBC = outline business case, ITN = invitation to negotiate, OJEU = Official Journal of European Union