This procedure applies to work undertaken without a building warrant having been obtained (where one was required). It applies only to work undertaken after 1 May 2005. This is not a means of circumventing the technical standards as you will require to demonstrate the work meets the standards in force at the time of submitting the application - not when the work was carried out.

How to make application

1. Submit a completed icon Completion Certificate with no Building Warrant for submission [71Kb], accompanied by
2. Two sets of plans and specifications
3. The appropriate fee

What happens to my application

  • We will assess the application for compliance (in some cases an inspection will take place at this time).
  • We will inform you if the application fails to comply and give you the opportunity to make the necessary changes if required.
  • You will have to make the changes on site if required.
  • We will then arrange a mutually suitable time for an inspection to be undertaken.

Contact details

Building Standards

Pullar House, 35 Kinnoull Street, Perth, PH1 5GD
Tel 01738 475300